Estonia: data centres and large consumers seek 3,000 MW of grid connections against a 1,700 MW peak
Two data centres planned in Estonia, at Hüüru and Risti, would each have around 200 MW, more than 10% of last winter's peak demand, says a professor at Tallinn University of Technology. He proposes that developers also bring new generating capacity, following a model under discussion in Finland.
EuroEnergy Newsroom · Estonia · 1 min read
The large data centres planned in Estonia could consume a significant share of the country's electricity, Mart Landsberg, a professor at Tallinn University of Technology, told ERR News. He cited two projects, one at Hüüru near Tallinn and another at Risti, both designed for a capacity of roughly 200 MW.
The figures. According to the professor, Estonia's peak demand in the highest-demand hour last winter was about 1,700 MW, so a single 200 MW centre would account for more than 10% of that level. Annually, such a facility could use 1.3–1.6 TWh, equivalent to 20–25% of the country's annual electricity consumption. Landsberg cited Elering data showing that connection requests from data centres and other large consumers total approximately 3,000 MW.
The proposal. To keep the new consumers from pushing up market prices by competing for existing capacity, the professor suggests that developers secure additional generation, through their own power plants or long-term agreements. He pointed to a regulatory change under discussion in the Finnish parliament that would impose such an obligation on grid connection, and cited as an example the Risti project, developed alongside solar and wind generation and battery storage.
Background. The company Sunly filed a detailed-plan application in February for the 180 MW campus at Risti, with an estimated investment of over €1.7 billion, ERR reported. According to DatacenterDynamics, Magnora has acquired 50% of the project, whose first phase could reach 180 MW and later 400 MW, next to an energy park with 244 MWp of solar, 144 MW of batteries and 44 MW of wind in development. Connection requests do not automatically turn into completed projects, the professor stressed.