Switzerland: SBB can automatically restore traction power after a blackout in five minutes instead of hours

Swiss Federal Railways (SBB) has rolled out nationwide a system that automatically restores power to the rail network within five minutes after a widespread blackout. The decisive test took place on the night of 12–13 November in Ticino, where the grid was back after 3 minutes and 5 seconds, according to SRF.

EuroEnergy Newsroom · Switzerland · 2 min read

Un tren de intervenție roșu al SBB, tras de o locomotivă diesel, trece pe lângă vechea clădire de piatră a substației feroviare de la Giornico, în Ticino, sub stâlpi și linii electrice; imagine ilustrativă
Foto: Kabelleger / David Gubler · CC BY-SA 4.0 · Wikimedia Commons

SBB has announced that, after a widespread power failure (blackout), it can now automatically restore its traction power grid within five minutes instead of the several hours needed until now. The system has been available across Switzerland since 13 November 2026, following a successful test during normal train operations.

How it works. A power grid must always be in balance: exactly as much electricity must be produced as is consumed. That is why restarting after a blackout is demanding and has so far been done manually, SBB explains. The new system keeps the power plants ready to generate and rebuilds the grid automatically. According to SRF, the plants rely on automation and fast-start functions.

The test. SBB trialled the system during 2026 in the Ticino traction power grid, most recently on the night of 12–13 November. At 2:20 a.m. the energy control centre in Zollikofen (canton of Bern) cut the traction power in Ticino, reported SRF, which attended the test. Restoration took 3 minutes and 5 seconds. Around 20 trains were standing in the region at the time, and a freight train was left without power in the Gotthard Base Tunnel. Simulations and trials in test environments began in 2021. Other grid operators can also buy the system, the company says.

Background. On 22 June 2005, SBB’s entire traction power grid failed for several hours: around 2,000 trains came to a halt and 200,000 passengers were stranded. The Swiss rail power grid is separate, with its own hydropower plants and high-voltage lines, and runs at 16.7 Hz and 15,000 V, compared with 50 Hz in the household grid, according to watson. About a quarter of SBB’s traction power comes from electricity converted from the general grid, according to SRF. On its grid restoration page, SBB cites the April 2025 blackout in Spain and Portugal as evidence that such outages can occur at any time.

Real-time data for the country are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page