Nuclear23 Nov 2026

European Commission lists the new Bohunice reactor among drivers of Slovakia’s deficit; the 2027 budget sets aside €100 million

In its autumn forecast, the European Commission names construction of the Jaslovské Bohunice nuclear power plant among the main factors pushing Slovakia’s deficit to 5.0% of GDP in 2027. According to the Council for Budget Responsibility, quoted by Pravda, the project costing at least €10.9 billion has €100 million in next year’s budget.

EuroEnergy Newsroom · Slovakia · 2 min read

Turnurile de răcire ale centralei nucleare Jaslovské Bohunice, lângă stația electrică a centralei; imagine ilustrativă din 2008
Foto: Michal Jančina · CC BY 3.0 · Wikimedia Commons

The new nuclear power plant at Jaslovské Bohunice has entered Brussels’ deficit calculations. In its autumn economic forecast, the European Commission writes that the main factors raising Slovakia’s deficit are public investment in defence, the construction of the nuclear power plant in Jaslovské Bohunice and national co-financing of EU projects. The daily Pravda examined on Sunday what the project means for public finances.

The figures. The Commission expects a deficit of 4.4% of GDP in 2026, 5.0% in 2027 and 5.5% in 2028, while public debt would rise from 63.4% of GDP in 2026 to 69.5% in 2028. According to the Council for Budget Responsibility (RRZ), quoted by Pravda, the 2027 budget earmarks €100 million for the plant, estimated to cost at least €10.9 billion, with no further sums for the years after 2027.

What the fiscal council says. In its assessment of the 2027–2029 budget, the RRZ warns that if the financial transaction tax is abolished from 2028 and some spending, including on the new nuclear plant, continues after 2027 without compensation, the deficit could reach 6.0% of GDP in 2028 and 6.5% in 2029. "The budget documents do not make it sufficiently clear what specific expenditure this amount is meant to cover," Pavol Majher, head of the RRZ’s budget analysis and forecasting department, told Pravda.

The project. The new unit, of up to 1,200 MW, is being prepared by the state-owned Jadrová energetická spoločnosť Slovenska (JESS). On 28 October JESS signed a contract with Westinghouse for the initial technical and design study; the first phase, worth five million dollars, is paid for by the US State Department, according to Pravda. Construction is due to start next year and finish around 2040, according to a document approved by the government in September.

What comes next. Prime Minister Robert Fico has said the construction contract could be signed in 2027 and acknowledged a delay of eight to ten months. It will also matter whether statisticians classify JESS in the general government sector: its spending and loans would then count directly towards Slovakia’s deficit and debt.

Real-time data for the country are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page