Energy policy23 Nov 2026

Bulgaria: Toplofikatsia Sofia had completed only 19% of its investments by September, energy minister says

Bulgaria's Energy Minister Iva Petrova told bTV that the problems at Toplofikatsia Sofia appear to be organisational: by September only 19% of its investment programme and 31% of its repair programme had been completed. The district heating company's debts to Bulgargaz and BEH exceed €1.3 billion.

EuroEnergy Newsroom · Bulgaria · 2 min read

Turnurile de răcire și coșurile centralei termice TETs Sofia a companiei Toplofikatsia Sofia, la amurg
Foto: Deensel · CC BY 2.0 · Wikimedia Commons

Bulgaria's Energy Minister Iva Petrova said on Sunday evening on bTV's "Zashto" programme that the country's energy system is prepared for winter, but that the situation at the district heating company Toplofikatsia Sofia remains extremely critical, the BTA news agency and the daily 24 Chasa reported. She distinguished between the company's long-term future and the immediate problem of the Sofia neighbourhoods where residents are not receiving adequate heating and hot water in November.

The figures. According to the minister, inspections showed that by September the company had completed only 19% of its investment programme and 31% of its repair programme, shortly before the start of the heating season. As of 30 September, substations were out of service because of breakdowns lasting more than two months, and the company had only five emergency crews, Petrova said. Toplofikatsia Sofia's debts to the state-owned Bulgargaz and Bulgarian Energy Holding (BEH) exceed €1.3 billion, of which about €900 million are receivables of Bulgargaz.

Prices. Petrova reaffirmed that household electricity and district heating prices will remain unchanged during the current regulatory period, until June 2027, while natural gas will see a moderate increase, offset by compensation for households. She pointed out that unchanged prices do not necessarily mean unchanged bills, as consumption rises in winter. The Chiren underground gas storage facility is around 72% full, against a European average of 69%, the minister added.

What comes next. Petrova welcomed the proposal for the World Bank to prepare technical and financial analyses for Toplofikatsia Sofia, which is owned by Sofia Municipality. For the equipment bought for the Belene nuclear power plant, several options are being considered, including a sale or building nuclear capacity with Ukrainian participation and European financing; the options will be assessed in the forthcoming strategy for sustainable energy development, the minister said.

Real-time data for the country are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page