Bulgaria: a stopped pump cut Kozloduy Unit 6 to 60% power, two days after its overhaul
According to the nuclear regulator, Unit 6 of the Kozloduy plant automatically reduced its power from 98.4% to 60.2% on the evening of 19 November after a circulation pump stopped, two days after restarting from its annual overhaul. The Bulgarian Ministry of Energy says the fault has been fixed, that it is unrelated to nuclear safety and that the unit was at 79% on Friday at noon.
EuroEnergy Newsroom · Bulgaria · 2 min read
Unit 6 of the Kozloduy nuclear power plant ran at reduced power after a technical fault on Thursday evening, 19 November, just two days after it had been reconnected to the grid following its annual overhaul. According to the Bulgarian Ministry of Energy, the fault was fixed the same day, and on Friday, 20 November, at 12:00, the unit had reached 79% of its power, with a further gradual increase under way.
What happened. According to the Bulgarian Nuclear Regulatory Agency (BNRA), quoted by public broadcaster BNT, the unit was running at 98.4% power when, at 17:14, the second circulation pump stopped after a technological protection was triggered by the high temperature of the oil supplying the pump bearings. The automatic protection systems reduced power to 60.2%. The oil temperature had risen because of a reduced flow of cooling water. After the flow was restored, at 18:30, the unit was unloaded to 30% so that the main circulation pump could be started.
Safety. The Ministry of Energy says the situation is unrelated to the nuclear safety of the plant. The BNRA stated, according to BNT, that the limits and conditions for safe operation were not exceeded and that the radiological situation was not affected. An inspection is under way to establish the causes.
The grid figures. ENTSO-E data published by Energy-Charts show that Bulgaria's total nuclear generation, which also includes Unit 5, fell from about 1,940 MW in the afternoon to approximately 1,280 MW around 19:00. On Saturday morning, 21 November, it was back at about 1,900 MW.
Background. The annual overhaul of Unit 6 began on 8 October, and the reactor was reloaded with fresh nuclear fuel. The unit was reconnected to the power system on 17 November at 10:23, after a positive assessment by the BNRA, the ministry announced at the time. According to BNT, the unit has for years had problems with one of its steam generators, which is why it cannot run permanently at full rated power.
Real-time data for the country are on the country page