Brussels: BRUGEL orders Sibelga to anticipate congestion as two medium-voltage substations exceed guaranteed capacity
The Brussels energy regulator BRUGEL has paired its opinion on Sibelga’s 2027–2031 electricity network development plan with an injunction, demanding proactive capacity planning. Two transformer substations are already operating above their guaranteed capacity, at load rates of 109.9% and 104.7%.
EuroEnergy Newsroom · Belgium · 1 min read · updated 25 Nov 2026
The energy regulator of the Brussels-Capital Region, BRUGEL, published on 23 November its opinion on the 2027–2031 electricity network development plan proposed by distribution system operator Sibelga, together with an injunction. According to the regulator, the plan does not provide every guarantee that the network will cope with the increasingly widespread electrification of consumption.
What was decided. BRUGEL wants Sibelga to move from a reactive to a proactive approach: to include the Brussels economic acceleration zones and policy orientations that may affect demand in its planning assumptions, to better justify how investment is split between low and medium voltage, and to study alternatives to reinforcement, including flexibility. The regulator also demands close coordination with transmission system operator Elia.
The figures. According to opinion no. 423, the Voltaire 11 kV substation has a negative reserve of 2.48 MVA, a load rate of 109.9%, and the Démosthène substation one of 0.75 MVA, or 104.7%. De Greef is reported at 98.6% and Dunant at 91.7%. Reinforcement of one of the substations would only be possible in 2031. By contrast, the average load of low-voltage cables is 18%, even though the cable-laying programme rises from 123.9 km a year in 2027 and 2028 to 158.4 km a year from 2029 to 2031.
Delays. In 2025, only 32 of the 344 planned devices for monitoring medium/low-voltage transformers were installed, under 10%, and none of the 10 planned smart cabins. Sibelga cites delivery delays.
What comes next. Under the procedure described by BRUGEL, the final plan and the opinion go to the regional government; if it has not decided by 31 December, the plan is deemed approved.