Companies20 Nov 2026

Elektroprivreda BiH cannot guarantee 2027 power prices; mines delivered 700,000 tonnes less coal than planned

Elektroprivreda BiH general director Sanel Buljubašić told N1 that households will see no price increase before the end of 2026, but he cannot guarantee prices for 2027. The company is taking short-term loans of up to 50 million KM, and in ten months the mines delivered about 700,000 tonnes less coal than planned.

EuroEnergy Newsroom · Bosnia and Herzegovina · 2 min read

Termocentrala Kakanj a Elektroprivreda BiH, cu un coș înalt în dungi roșii și albe, văzută de peste râu, printre copaci de toamnă
Foto: Manfred Kopka · CC BY-SA 4.0 · Wikimedia Commons

Sanel Buljubašić, general director of Elektroprivreda BiH (EPBiH), said in an interview with N1 published on 19 November that there will be no new electricity price increase for households until the end of 2026. For 2027, however, he cannot give guarantees: the three-year business plan for 2027–2029 is not yet finished and is due to be adopted by the end of the year.

The figures. For businesses, offers for 2027 are up to 31% higher. EPBiH has concluded more than 2,800 contracts, while about 500 customers are still considering offers; contracted prices range from about 123 to 129 €/MWh. According to the director, about 70% of customer bills fall under the green tariff, and the average bill is about 50.50 KM.

Coal. In the first ten months the mines delivered about 700,000 tonnes less coal than planned, and their total debts exceed 1.2 billion KM. The company is short of about 1.2 million tonnes, which it must buy on the market, the SEF portal notes, and thermal plants have produced about 80% of plan this year. Buljubašić admitted that the failure to raise coal output is the biggest setback of his term: “We did not succeed, I did not succeed.”

Finances. EPBiH plans short-term borrowing of up to 50 million KM; the director says this is a matter of strained short-term liquidity, not insolvency. According to the revised business plan described by Oslobođenje, the first two loans, totalling 35 million KM, are already signed, and 2026 investment has been cut from 426.3 to 196.4 million KM. Advances of 119.4 million KM paid to the mines for undelivered coal are to be converted into long-term loans at 2% interest.

What comes next. A document prepared for the Federation government says the current organisational model of the group cannot be sustained. Buljubašić proposes a special law declaring strategic energy projects to be in the public interest, because permits are often delayed by administrative disputes.

Real-time data for the country are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page