Belarus: the 330 kV Mozyr–Petrikov–Mikashevichi line, about 150 km long, enters commissioning; completion due in December
The 330 kV Mozyr–Petrikov–Mikashevichi power line, about 150 km long, which will link the Gomel and Brest regions, is nearing completion: construction is wrapping up and specialists have started commissioning. According to Gomelenergo, all stages are to be completed by the end of December.
EuroEnergy Newsroom · Belarus · 2 min read · updated 25 Nov 2026
Regional power company Gomelenergo said on 23 November, through the state news agency BelTA, that two major grid modernisation projects in the Gomel region are due to be completed by the end of the year. The most important is the 330 kV Mozyr–Petrikov–Mikashevichi line, about 150 km long, described as the largest energy project in recent years in the country’s south-east.
State of works. According to Gomelenergo, construction and installation works are nearly finished and specialists have moved on to the commissioning stage. All stages are to be completed by the end of December, in line with an instruction from the head of state. In parallel, the reconstruction of the two 330 kV substations, Mozyr and Mikashevichi, is nearing completion. The line will connect the power systems of the Gomel and Brest regions.
Context. The project was set out in Decree No. 358 “On improving the reliability of power supply”, signed by Alexander Lukashenko on 12 September 2024, with the aim of improving the reliability of supply to the Mozyr power hub. The client is Gomelenergo, the general designer Belenergosetproekt and the general contractor Zapadelektrosetstroy, BelTA reported at the time. According to the portal Myfin.by, the decree set a special procedure that exempted the project from environmental impact assessment, public discussion and ecological expertise.
What comes next. Also in December, the Zhlobin Electric Networks branch is due to complete grid modernisation in the Rogachev district, provided for by the programme to overcome the consequences of the Chernobyl disaster. In the village of Kisteni the distribution network is being rebuilt: more than 13 km of overhead lines and five transformer substations are being dismantled and replaced with more than 16 km of new overhead lines, 6 km of 10 kV cable and 11 transformer substations. The project provides for switching heating, hot water and cooking to electricity in 192 of the 254 houses, the newspaper SB. Belarus Segodnya also reported.
More news
Comments
Be the first to comment.
