Five of the 18 operators who will soon start work at the first unit of the Akkuyu nuclear power plant are citizens of Türkiye, Anton Dedusenko, chairman of the board of Akkuyu Nuclear, told Anadolu Agency (AA). According to him, they will be the first Turkish citizens to work as operators at a nuclear power plant.
How they were selected. Vetting has two stages: operators first sit a qualification exam administered on site by Rosatom, and the results are then approved by Türkiye's regulator, according to AA. The remarks were made at the "World Atomic Days" event organised by Rosatom in Antalya alongside the COP31 UN climate conference.
The figures. The project plans to train around 600 Turkish engineers, more than half of whom already work at the plant. Once the units are commissioned, at least 4,000 people, Turkish and Russian citizens, will work at Akkuyu, and each job is expected to create 10 more in the region. Dedusenko estimates the project's effect on Türkiye's GDP will exceed 50 billion dollars, roughly double the investment.
Context. Energy and Natural Resources Minister Alparslan Bayraktar said on 13 November, also in Antalya, that Türkiye will begin the physical start-up of the first Akkuyu reactor "within weeks", according to AA. The government targets 10 GW of installed nuclear capacity by 2040 and at least 20 GW by 2050, and Türkiye is in talks with technology providers for its second and third plants.
What comes next. At the peak of construction around 35,000 people worked on the site; the number is falling as the first of the four units nears commissioning, and new roads have shortened travel time to the plant, according to AA.