Spain · island electricity system

Electricity in Tenerife

Demand, generation and electricity links of Tenerife, from Red Eléctrica's official data, every five minutes.

live Source: Red Eléctrica de España (REE) · last reading 21/10/2026, 07:05:00

← Electricity in the Canary Islands

Grid snapshot

Demand, generation and balance, updated every minute.

Source: Red Eléctrica de España (REE) · last reading 21/10/2026, 07:05:00

Demand now
436MW
▼ −20 MW vs a day ago
Tenerife · The island's own data
Local generation
443MW
102% of demand
Tenerife · The island's own data
Received over the links
0MW
0% of demand
Tenerife · The island's own data
Sent over the links
8MW
Tenerife · The island's own data
Renewables
22.2%
of local generation
Tenerife · The island's own data
CO₂ emissions
517g/kWhestimated
229 tCO₂/h
Tenerife · The island's own data

What covers demand right now

The categories are those published by Red Eléctrica, unaltered.

Combined cycle: 243 MW Wind: 99 MW Vapor turbine: 64 MW Internal combustion engines (ICE): 37 MW 436 MW demand
  • Combined cycle 243 MW54.9%
  • Wind 99 MW22.2%
  • Vapor turbine 64 MW14.5%
  • Internal combustion engines (ICE) 37 MW8.4%

Leaving the island: Tenerife-La Gomera link 8 MW

Demand over the last 24 hours

Actual, scheduled and forecast demand from the system operator, in MW.

MW

300400500600actualscheduledforecast10:0013:0016:0019:0022:0001:0004:0007:0010:0013:00300400500600actualscheduledforecast13:0019:0001:0007:0013:00

actual scheduled forecast

La Gomera 8 MW export TENERIFE cross-border energy flows SPAIN · ISLAND ELECTRICITY SYSTEM Import into Tenerife (energy coming in) Export from Tenerife (energy going out) Total cross-border exchange 8 MW Import 0 MW Export 8 MW 0 50 100 200 km N

The arrows and figures are measurements, as of 21 October at 06:05. The transmission grid is not shown: we do not have its routes for this country yet.

Interconnections and submarine cables

The flow on each link is the one published by REE, every five minutes. The diagram is not to scale.

ProjectFlow now End pointsVoltageCapacity LengthCables In service sinceSources
Fuerteventura-Lanzarote linkEnlace Lanzarote-Fuerteventura a 132 kV (Playa Blanca–La Oliva)
2 MW(Lanzarote → Fuerteventura)
La Oliva 132 kV (Fuerteventura)↔ Playa Blanca 132 kV (Lanzarote)
132 kValternating current
120 MVA
14.5 km under the sea
maximum depth 80 m
—
2022
Tenerife-La Gomera linkNuevo enlace eléctrico submarino, doble circuito, Chío (Tenerife) – El Palmar (La Gomera) a 66 kV
8 MW(Tenerife → La Gomera)
Chío 66 kV (Guía de Isora, Tenerife)↔ El Palmar 66 kV (San Sebastián de La Gomera)
66 kValternating current
2 × 50 MVA
36 km under the sea
maximum depth 1,145 m
—
2026

There are two cables between Lanzarote and Fuerteventura (the 66 kV one from 2005 and the 132 kV one from 2022); REE publishes a single flow, the total of both, and that is what is shown.

Who supplies the electricity?

System operator and transmission owner

Red Eléctrica de España (REE) operates the electricity system, balances generation and demand, runs the transmission grid and the submarine cables, and publishes the official real-time data. [1]

Distributors

The local grid, meters, outages and connections are the responsibility of the area's distributor. The CNMC register lists two companies operating in the Canaries. There is no official figure for the territory each one covers. [1] [2]

Retailers (comercializadores)

Consumers choose their retailer, under the same rules as in mainland Spain. On the regulated market (PVPC) supply comes from the reference retailers; on the free market, from any authorised retailer. No company is the islands' sole supplier. [1]

Reference retailers with national scope (CNMC list, consulted on 2026-09-18) [1]

  • Energía XXI Comercializadora de Referencia, S.L.U. (Endesa)
  • Curenergía Comercializador de Último Recurso, S.A.U.
  • Comercializadora Regulada, Gas & Power, S.A.
  • Baser Comercializadora de Referencia, S.A.
  • Comercializador de Referencia Energético, S.L.U.

CNMC's official list of all retailers →

Generators

The plants are dispatched by REE. The list includes only what could be confirmed in official sources; unconfirmed fields are left empty.

Renewable capacity installed in the Canary system: 1,031 MW as of December 31, 2025, 30.0% of the generation fleet (REE). [REE]

PlantLocationOwner TechnologyCapacityStatus Sources
Central térmica de Granadilla
TenerifeGranadilla de Abona
Unión Eléctrica de Canarias Generación, S.A.U. (grupo Endesa)
Combined cycle
Gas turbine
Vapor turbine
Internal combustion engines (ICE)
—
in service
Central térmica de Candelaria (Las Caletillas)
TenerifeCandelaria
Unión Eléctrica de Canarias Generación, S.A.U. (grupo Endesa)
Vapor turbine
Gas turbine
—
in service

Electricity market price applicable to the Canary Islands

This price is not an individual commercial tariff and may be common to several islands.

Spain · day-ahead market (OMIE)

Price now
265.57EUR/MWh
0.266 EUR/kWh (EUR/MWh ÷ 1000)
Spain · day-ahead market (OMIE)
Average price today
146.97EUR/MWh
Spain · day-ahead market (OMIE)
Cheapest hour
0.42EUR/MWh
15:00–16:00
Spain · day-ahead market (OMIE)
Most expensive hour
284.93EUR/MWh
21:00–22:00
Spain · day-ahead market (OMIE)
Price by hour, today — EUR/MWh, Madrid time
010020030000:00 — 177.86 EUR/MWh0001:00 — 178.48 EUR/MWh02:00 — 167.75 EUR/MWh03:00 — 161.67 EUR/MWh0304:00 — 160.48 EUR/MWh05:00 — 166.33 EUR/MWh06:00 — 184.24 EUR/MWh0607:00 — 226.08 EUR/MWh08:00 — 258.25 EUR/MWh09:00 — 196.60 EUR/MWh0910:00 — 78.71 EUR/MWh11:00 — 2.00 EUR/MWh12:00 — 0.95 EUR/MWh1213:00 — 0.75 EUR/MWh14:00 — 0.68 EUR/MWh15:00 — 0.42 EUR/MWh0.421516:00 — 0.78 EUR/MWh17:00 — 68.88 EUR/MWh18:00 — 193.22 EUR/MWh1819:00 — 255.14 EUR/MWh20:00 — 284.49 EUR/MWh21:00 — 284.93 EUR/MWh2852122:00 — 253.92 EUR/MWh23:00 — 224.61 EUR/MWh010020030000:00 — 177.86 EUR/MWh0001:00 — 178.48 EUR/MWh02:00 — 167.75 EUR/MWh03:00 — 161.67 EUR/MWh04:00 — 160.48 EUR/MWh05:00 — 166.33 EUR/MWh06:00 — 184.24 EUR/MWh0607:00 — 226.08 EUR/MWh08:00 — 258.25 EUR/MWh09:00 — 196.60 EUR/MWh10:00 — 78.71 EUR/MWh11:00 — 2.00 EUR/MWh12:00 — 0.95 EUR/MWh1213:00 — 0.75 EUR/MWh14:00 — 0.68 EUR/MWh15:00 — 0.42 EUR/MWh0.4216:00 — 0.78 EUR/MWh17:00 — 68.88 EUR/MWh18:00 — 193.22 EUR/MWh1819:00 — 255.14 EUR/MWh20:00 — 284.49 EUR/MWh21:00 — 284.93 EUR/MWh28522:00 — 253.92 EUR/MWh23:00 — 224.61 EUR/MWh

the cheapest third of the hours the most expensive third

The Canary Islands have no electricity market of their own: REE dispatches the plants, with no bidding. The figures are those of the Spanish day-ahead market (OMIE), in EUR/MWh — a wholesale price, not a bill. The price at which island demand buys its energy is derived from the daily average mainland price, shaped by the hourly profile of Canary demand (Royal Decree 738/2015, Annex I). BOE-A-2015-8646

The regulated PVPC price, paid by household consumers (in EUR/kWh), is published by e·sios for the Canary Islands too. We do not show it yet: access requires a personal token from REE.

What data exists and what does not

REE · Seguimiento de la demanda · REData · OMIE · Aviso legal REE