Windar Polska to build the 26 towers for the 390 MW BC-Wind offshore wind farm in the Baltic Sea
Siemens Gamesa has awarded Windar Polska the manufacture of 26 steel towers for the turbines of the BC-Wind offshore wind farm, which Ocean Winds is building about 23 km off the Polish coast. The first turbine components are due to be delivered in the first quarter of 2028, with installation set to begin in the second quarter.
EuroEnergy Newsroom · Poland · 2 min read
Siemens Gamesa, the turbine supplier for the BC-Wind offshore wind farm, has signed a contract with Windar Polska, the Polish subsidiary of Spain’s Windar Renovables, to produce 26 complete steel towers, developer Ocean Winds announced. According to the Energetyka24 portal, the agreement was signed at the Offshore Wind Poland 2026 conference, and Offshorewind.biz reports that the towers will be manufactured and assembled at Windar’s plant in Szczecin.
What the contract covers. Windar Polska will produce the tower sections, assemble them and fit the internal equipment: platforms, ladders and guides for high-voltage cables. Szczecin-based KK-Wind will supply the internal LV and SST platforms. Ocean Winds wants the project to benefit Poland beyond the energy infrastructure itself. “Producing key components of an offshore wind farm in Poland is an important element of this goal,” said Kacper Kostrzewa, Managing Director of Ocean Winds in Poland.
The figures. BC-Wind will have 26 Siemens Gamesa SG 15-236 turbines of 15 MW each, 390 MW in total, about 23 km from the coast. According to the developer, the farm could meet the annual electricity consumption of nearly 500,000 Polish households. Ocean Winds is a 50/50 joint venture of EDP Renewables and ENGIE, and BC-Wind is its first project in the Baltic Sea.
The timeline. The first turbine components are due to be delivered in the first quarter of 2028, with installation starting in the second quarter using a Cadeler O-class vessel; the installation port will be Terminal T5 in Gdańsk, about 92 km from the farm. The first monopile foundations arrived at the end of October at the offshore terminal in Świnoujście. According to Offshorewind.biz, the project needs 27 monopiles, 26 for the turbines and one for the offshore substation, and foundation installation is due to start in the first half of 2027.
Real-time data for the country are on the country page
More news
Comments
Be the first to comment.
