SmartestEnergy, the British subsidiary of Japan's Marubeni group, has signed two 20-year power purchase agreements (PPAs) for the Norfolk Vanguard West and East offshore wind farms being developed by RWE and KKR. The contracts cover 25% of the combined output of the two projects, totalling around 2.8 GW, which are due to be fully operational from 2030.

EuroEnergy Newsroom · United Kingdom · 2 min read

Trei turbine eoliene offshore cu fundații galbene în parcul Scroby Sands, în Marea Nordului, în largul coastei Norfolk; imagine ilustrativă
Foto: Martin Pettitt · CC BY 2.0 · Wikimedia Commons

SmartestEnergy announced on 25 November that it had been selected, following a competitive process, as route-to-market provider for Norfolk Vanguard West and Norfolk Vanguard East, two North Sea offshore wind farms jointly owned by RWE and KKR. The company has signed two 20-year power purchase agreements (PPAs), backed by the projects' Contracts for Difference (CfDs), covering 25% of their combined output.

What was signed. According to SmartestEnergy, these are two of the largest PPAs in the company's history, and the deal is financially backed by its parent company, Japan's Marubeni group. “These are two of our largest PPAs to date,” said Beth Reid, acting chief executive of SmartestEnergy. Law firm Shoosmiths, which advised the projects, said several long-term PPAs were negotiated in parallel and, together with the CfDs, underpin the financing.

The figures. Each wind farm will have around 1.4 GW, roughly 2.8 GW in total, located 50–80 km off the Norfolk coast in East Anglia. According to RWE, the total investment is around £12bn, including transmission infrastructure, and the wind farms will be able to supply the equivalent of around three million UK homes. The non-recourse financing, announced on 11 November, comprises £11.1bn in cash facilities and £1.7bn in ancillary facilities from 35 banks, including £1bn from the National Wealth Fund; RWE describes it as the largest ever project financing in UK offshore wind.

Context. In January 2026, in Allocation Round 7 (AR7), each project won a 20-year inflation-indexed CfD at a strike price of £91.20/MWh in 2024 prices. KKR has acquired 50% of each project, and RWE leads delivery on behalf of the joint venture.

What comes next. Offshore construction is due to begin in early 2027: the first foundation at Vanguard West is planned for the first half of the year, followed by Vanguard East. Onshore cable works and substation construction are already well advanced, and full commissioning is expected in 2030.

The country's real-time data are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page