Companies24 Nov 2026

PPC: the 300 MW data centre at Agios Dimitrios would consume 2.33 TWh a year, environmental impact study shows

The environmental impact study for the data centre that PPC (ΔΕΗ) is preparing at the site of the Agios Dimitrios lignite plant near Kozani foresees a maximum power draw of 300 MW and consumption of about 2.33 TWh a year, newmoney reports. PPC is negotiating the final agreement for the first phase with Amazon Web Services.

EuroEnergy Newsroom · Greece · 2 min read · updated 25 Nov 2026

Termocentrala pe lignit Agios Dimitrios de lângă Kozani, cu coșurile și turnurile de răcire; pe amplasamentul ei PPC plănuiește centrul de date
Foto: Thpanagos · CC BY-SA 3.0 · Wikimedia Commons

The data centre that PPC (ΔΕΗ) is preparing at the site of the Agios Dimitrios lignite power plant in Kozani, Western Macedonia, would have a maximum power draw of 300 MW, of which 240 MW for IT equipment, according to a 737-page environmental impact study whose details were published on Tuesday by the business portal newmoney. In September PPC signed a memorandum of understanding with Amazon Web Services (AWS) for the project.

The figures. At full load the centre would consume about 2.33 TWh of electricity a year, 90.3% of it for IT equipment. Four buildings are planned, each with five server halls of 12 MW. Power would come from the 400 kV substation of transmission operator ADMIE at Agios Dimitrios through four new underground cable lines, and 144 diesel generators, 12 of them as reserve, are planned for emergencies.

The regional grid. According to ADMIE and distribution operator DEDDIE data cited in the study, about 2.9 GW of wind and solar parks operate in the area and a further 3.4 GW hold final connection offers; the data centre would represent about 5% of these 6.3 GW. Cooling water, about 203,260 m³ a year, would come from the Polyfytos reservoir, and the recoverable heat, with a thermal capacity of 93.91 MW, could be used to heat neighbouring communities.

What comes next. According to newmoney, PPC chief executive Georgios Stassis told analysts that the group expects the connection terms to be finalised in the coming weeks and that negotiations with AWS on the first phase are progressing. A final investment decision on an expansion to 1 GW is expected in the first half of 2027, and Amazon holds a right of first refusal until the end of May 2027. The outlet ot.gr notes that PPC shares fell below 23 euros again on Monday, after US President Donald Trump threatened a tax on American companies building data centres outside the United States.

The country's real-time data are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page