Norway: NVE approves a new 132 kV line between Dokka and Gjøvik, replacing two lines more than 60 years old

The Norwegian Water Resources and Energy Directorate (NVE) has granted Elvia a licence for a 132 kV overhead line of about 30 km between Dokka and Gjøvik, via the new Skyberg substation. The line replaces two lines built between 1951 and 1962, and Elvia estimated the investment at NOK 445 million.

EuroEnergy Newsroom · Norway · 2 min read

Stâlp de linie electrică de înaltă tensiune cu izolatoare, fotografiat de jos, pe cer înnorat, pe una dintre liniile care intră în orașul Gjøvik; nu este linia nouă aprobată, imagine ilustrativă
Foto: Øyvind Holmstad · CC BY-SA 4.0 · Wikimedia Commons

The Norwegian Water Resources and Energy Directorate (NVE) on 19 November granted grid company Elvia a licence for a new 132 kV overhead power line between Dokka and Gjøvik in Innlandet county, and announced the decision on 20 November. The project crosses the municipalities of Nordre Land, Søndre Land and Gjøvik.

What was decided. According to NVE, the line has two sections: 18 km between Dokka and the Skyberg substation and 13 km between Skyberg and Gjøvik. The new line will be built parallel to the current one, on the alternative north of Lake Landåsvatnet, and the old 132 kV lines between Dokka and Gjøvik will be dismantled. “The power line on the section between Dokka and Gjøvik is old and must be renewed,” said Ingrid Myrtveit, head of section at NVE. Elvia was also granted expropriation rights for the necessary easements.

The figures. In its licence application of November 2025, Elvia stated that the two existing lines were built between 1951 and 1962 and estimated the investment in the new double-circuit line at NOK 445 million. The company calculated that grid losses would fall by about 24 GWh a year compared with the no-investment option. The new pylons will be 25–35 m tall, against 15–20 m today, but the cleared corridor will be narrower.

The conditions. NVE requires bird diverters on the conductors, pylons painted in colours that blend with the background where this helps camouflage them, limits on forest clearing, especially through valuable nature types, and protection of cultural heritage sites along the route.

What comes next. Elvia must prepare a detailed plan for construction and impact mitigation, which NVE must approve before work begins. According to the application, the new Skyberg substation is due to enter service in 2027, when capacity between Dokka and Skyberg would become a constraint.

Real-time data for the country is on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page