Moldova's government has declared a 30-day state of alert in the energy sector from 25 November, after the state of emergency expired. The National Crisis Management Commission cut electricity export capacity for 17:00–22:00 to zero and ordered a cut of at least 50% in electricity used for public lighting.

EuroEnergy Newsroom · Moldova · 2 min read

Doi stâlpi metalici de înaltă tensiune cu izolatori și conductoare, la amurg; imagine ilustrativă, nu din Republica Moldova
Foto: Mostafameraji · CC0 · Wikimedia Commons

Moldova's government declared a nationwide state of alert for 30 days starting on 25 November 2026, as the state of emergency expired, the National Crisis Management Centre announced. The authorities stress that the measure is preventive: it does not mean the risks have materialised, nor that any interruptions in energy supply are planned.

What was decided. Under Decision No. 12 of 25 November, the National Crisis Management Commission ruled that between 17:00 and 22:00 the electricity export capacity allocated for the following day will be set to zero, so that available energy is used first at home. Hospitals, emergency services, water intake and pumping stations and district heating plants have absolute priority for supply. If energy is insufficient and the usual purchasing options are exhausted, Moldelectrica may request emergency energy from neighbouring systems; disconnections remain a last resort.

Consumption. Central and local public authorities will cut electricity use for public lighting by at least 50%, and public buildings and shops will reduce indoor lighting by at least 30% where possible. Decorative, architectural and advertising lighting will be switched off, Radio Chișinău and Bani.md also report. District heating plants will be able to produce more electricity, within their technical limits.

Renewables and storage. The commission fast-tracked grid connection of solar and wind plants equipped with batteries and of storage facilities: completed projects get priority, and for those under construction, connection permits that expired from July 2026 can be extended by up to three months.

Context. Among the risk factors, the authorities list the reduction from December of guaranteed electricity import capacity from Romania, dependence on imports and short-term purchases, and lower generation capacity in the region, including because of attacks on Ukraine's energy infrastructure. Energy Minister Dorin Junghietu told Moldova 1, as quoted by Ziarul de Gardă, that Ukraine has set its electricity export capacity to zero and that Moldova covers its shortfall, especially at peak hours, with imports from Romania.

Real-time data for the country are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page