Kosovo: EU confirms Kosovo B unit B1 will not be ready by 25 November and adds EUR 5.6 million
The European Union Office in Kosovo has confirmed that the installation of electrostatic filters at unit B1 of the Kosovo B power plant will not be completed by the contractual deadline of 25 November 2026. The EU has allocated an additional EUR 5.6 million for equipment and shift workers, in a project to which it contributes about EUR 84 million.
EuroEnergy Newsroom · Kosovo · 2 min read
Unit B1 of the Kosovo B lignite-fired power plant, under environmental upgrade works since April, will remain out of operation beyond 25 November 2026, the contractual completion date. The European Union Office in Pristina confirmed the delay in replies to the KALLXO.com portal and the daily Gazeta Express, citing “technical, logistical” challenges and implementation difficulties.
What the EU says. According to the EU Office, the works began in April 2026 and will continue beyond the contractual deadline. To speed them up, the EU has allocated a further EUR 5.6 million for specialised equipment and for mobilising additional workers in shifts, has strengthened contract supervision and is working with the authorities, the power company KEK, the contractor and the supervisor. The EU's total contribution to the project is about EUR 84 million; the works are carried out by a consortium from Germany, Poland and the United Kingdom, under the supervision of an independent engineering firm.
The figures. After the upgrade, dust emissions are expected to fall by up to 35 times, nitrogen oxide emissions fourfold, and electricity output to rise by about 10%, according to the EU, as quoted by Buletini Ekonomik and Ekonomia Online.
Background. On 16 November the government in Pristina adopted 60-day emergency measures for electricity supply, citing in its reasoning the outage of unit B1 and the uncertainty over its restart. Economy Minister Artane Rizvanolli said the institutions do not yet have a new completion date, KALLXO.com reported. KEK stated that the electrostatic filter project is financed, contracted and managed by the EU, with the company only a beneficiary, and asked that it not be confused with the turbine modernisation, KEK's own investment.
What comes next. The goal remains to complete the works as quickly as possible without compromising technical quality, safety and environmental performance, the EU Office said. No new restart date has been announced.