Wind17 Nov 2026

Iceland: all 14 turbines at Vaðölduver, the first wind farm, are producing power, but below expectations

Landsvirkjun says all 14 turbines erected this year at Vaðölduver, Iceland's first wind farm, have delivered electricity to the grid, but output has so far been below expectations. The company aims to have the wind farm in full operation with 28 turbines in autumn 2027.

EuroEnergy Newsroom · Iceland · 2 min read

Clădirea centralei hidroelectrice Búrfell a Landsvirkjun, pe râul Þjórsá, la poalele muntelui Búrfell, în zona în care se află și parcul eolian Vaðölduver; imagine ilustrativă
Foto: Richard Bartz · CC BY-SA 3.0 · Wikimedia Commons

State-owned power company Landsvirkjun announced on 16 November that all 14 wind turbines erected this year at Vaðölduver have delivered electricity to the power system, each having run for at least ten days. The wind farm, the first of its kind in Iceland according to the company, was commissioned on 15 September 2026 and stands on a lava and sand plain at Vaðalda, east of the Þjórsá river and south of the Sultartangi dam.

Why output is lower. According to Landsvirkjun, production has so far been below expectations. The weather has been milder than the average of recent years and the turbines have not all run at the same time, so output has been intermittent while the wind farm is brought into full operation. The company says this commissioning phase is accounted for in its operating plan for the winter. On 11 November the news site Vísir reported, based on a reply from the company, that trial operation of the 14 turbines would last all winter.

The figures. On the power station's page, Landsvirkjun lists for 2026 an installed capacity of 60 MW and a generating capacity of 220 GWh a year, with 14 turbines in operation.

Work under way. Staff from Landsvirkjun and turbine maker Enercon are adjusting equipment and sensors and aligning communication between the wind farm's control system and Landsvirkjun's control centre. Landsvirkjun owns and operates the wind farm, while Enercon provides servicing under a contract. Among the next steps are system tests to confirm that Vaðölduver meets the requirements of transmission system operator Landsnet.

What comes next. Work at Vaðölduver continues until autumn 2027, and transport of turbines resumes in May 2027. The target is to have the wind farm in full operation with 28 turbines in autumn 2027.

Real-time data for the country is on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page