Iceland: the 220 kV Suðurnesjalína 2 line has been energised after almost two decades of preparation

Icelandic transmission system operator Landsnet energised the Suðurnesjalína 2 line on 20 November, a 220 kV link of about 30 kilometres between Hafnarfjörður and Njarðvíkurheiði. The Suðurnes peninsula thus gains a second connection to the transmission grid, after depending until now on a single line.

EuroEnergy Newsroom · Iceland · 1 min read

Stâlpi metalici în formă de Y ai unei linii de înaltă tensiune traversând o pajiște verde din Islanda, cu munți înzăpeziți în depărtare; imagine ilustrativă, nu linia Suðurnesjalína 2
Foto: Tristan Ferne · CC BY 2.0 · Wikimedia Commons

The Suðurnesjalína 2 line was energised on Friday, 20 November, at 4 p.m., announced Landsnet, Iceland’s transmission system operator. It is a 220 kV line between the Hamranes substation in Hafnarfjörður and Njarðvíkurheiði, linking the Suðurnes peninsula with the capital area.

The figures. According to Landsnet data cited by Vísir, the line is about 30 kilometres long, of which roughly 28.5 km is overhead and 1.6 km is underground cable, near Hamranes. It has 86 steel towers, six of them monopoles in Hafnarfjörður, about 215 tonnes of aluminium conductors and 800 tonnes of steel in the towers.

Why it matters. Until now, the 132 kV Suðurnesjalína 1 was the only route for transmitting electricity between Suðurnes and the capital area. On the project page, Landsnet notes that an outage of that line almost without exception caused power cuts in the region. The second connection should make maintenance and response to faults easier, improve security of supply and allow power to be transmitted from the plants on Reykjanes. “It increases transmission capacity into the area, and also resilience, flexibility and security of supply,” Landsnet CEO Ragna Árnadóttir told RÚV.

Context. Preparations began in 2005 and construction in 2016, but work was halted in 2017 after a Supreme Court ruling on expropriation. The project went through a new environmental assessment and permitting process, and work on the overhead section resumed in July 2024. According to RÚV, Landsnet has paid landowners more than ISK 300 million in compensation.

What next. The mayor of Reykjanesbær, Vilhjálmur Árnason, told RÚV that the region already needs a third line, Suðurnesjalína 3, which would add resilience and open possibilities for new energy sources.

The country's real-time data are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page