Electricity19 Nov 2026

Finland: nuclear output halved in October, while electricity imports rose by about 90%

With Loviisa 1 and Olkiluoto 3 in maintenance for almost the whole month, Finnish nuclear plants generated about 1.5 TWh in October, roughly half of last year’s level, according to Energiateollisuus statistics published on 19 November. The gap was filled by hydro, wind and imports, and the average wholesale price was 38 €/MWh, the association said.

EuroEnergy Newsroom · Finland · 1 min read

Centrala nucleară Loviisa, cu cele două clădiri ale reactoarelor și coșul înalt, văzută peste un golf cu stuf
Foto: Thomas Gartz · CC BY-SA 4.0 · Wikimedia Commons

Monthly statistics published on 19 November by Energiateollisuus, the Finnish energy industry association, show an unusual October: electricity consumption was 7.1 TWh, 0.8% more than in October 2025, but nuclear output fell by half because the Loviisa 1 and Olkiluoto 3 reactors were in maintenance for almost the whole month.

The figures. Nuclear plants generated 1,536 GWh, compared with 2,983 GWh a year earlier, and covered about 22% of consumption. Hydropower plants delivered about 1.5 TWh, 53% more than last year, and wind farms 2.8 TWh, almost 20% more. Imports rose by about 90% to 1.1 TWh, of which 1.05 TWh came from Sweden, making Finland a net importer of 0.4 TWh; most exports, about 0.6 TWh, went to Estonia.

The price. According to Energiateollisuus, quoted by the publication Energiauutiset, the average wholesale price in Finland was 38 €/MWh, very low for the season, while in Central Europe it ranged from 165 to over 240 €/MWh. “October was exceptional in many ways,” said the association’s CEO, Jukka Leskelä.

Background. October was warmer than usual, especially in the south of the country, and lower district heating demand cut combined heat and power output to 0.7 TWh, 9% less; municipal CHP plants produced 0.3 TWh, the lowest for an October since 1976, the association said. Industry consumed 2.9 TWh (−0.3%), and other categories, including households, services and data centres, 4.2 TWh (+1.7%).

What comes next. Olkiluoto 3 has a maintenance interval of a year and a half, so its next planned outage will be in spring 2028.

Real-time data for the country are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page