Finland: Parikkala municipality drops a five-year ban on battery storage projects above 2 MW
The municipal board of Parikkala, in South Karelia, decided unanimously on Monday, 23 November, not to impose for now a five-year construction ban on battery storage of at least 2 MW, according to the meeting minutes and a report by Yle. At the same meeting it launched a partial master plan for the municipality’s energy grid.
EuroEnergy Newsroom · Finland · 2 min read
The municipal board (kunnanhallitus) of Parikkala, a municipality in the South Karelia region, rejected a proposal to ban for five years the construction of battery energy storage facilities with a rated charging power of at least 2 MW. According to the minutes of the meeting on 23 November, board member Sakari Paakkinen (Centre Party) proposed that the ban not be imposed “at this stage”, and the proposal, seconded by Mika Härkönen, was adopted unanimously. The decision was reported on Thursday by the public broadcaster Yle.
What was decided. The rejected proposal would have covered the entire municipality, including areas with a detailed local plan, until 23 November 2031. At the same meeting the board approved the launch of a partial master plan for the energy grid covering the whole municipality. Three members holding positions in the governing bodies of the local distribution company Parikkalan Valo did not take part in the debate or the vote because of a conflict of interest, the minutes show.
The arguments. Paakkinen told Yle that the ban would have targeted a single company and that the concern about congestion on transmission operator Fingrid’s 110 kV line was based on a mistaken premise. He noted that Fingrid is planning a new 110 kV line between Imatra, Ruokolahti and Rautjärvi, to which factories in the Simpele area could connect, freeing capacity for other projects. Municipal manager Juho Jukkola rejected the idea that the ban was aimed at one company: the purpose was to give the municipality time to assess all energy projects, because permitting and construction of battery storage move much faster than land-use planning.
The figures. According to the meeting documents, available consumption capacity in Parikkala is preliminarily estimated at about 20 MW, while the storage projects known to the municipality total about 110 MW. Jukkola said the new Fingrid line does not reach Parikkala and will take years, and a 400 kV line to the municipality is not planned before 2035; until then Parikkala will have only one 110 kV transmission line.
What comes next. According to the municipal manager, the decision not to impose the ban could affect the preparation of the energy grid plan. “It is not unusual for proposals prepared by officials not to receive a positive decision,” Jukkola said.