Cyprus: MPs warn that retiring about 720 MW at the end of 2029 threatens the electricity supply
Cyprus's House plenary debated on 19 November the risk that the country will no longer be able to cover its electricity demand after old units at Dhekelia and Vasilikos, totalling about 720 MW, are retired at the end of 2029. MPs from AKEL, DISY and DIKO called on the government for urgent solutions.
EuroEnergy Newsroom · Cyprus · 2 min read
The plenary of the Cyprus House of Representatives on Thursday, 19 November, debated delays in critical energy projects at the request of AKEL, and the discussion focused on the risk that the island will be unable to cover its electricity needs from the start of 2030, according to Philenews and Politis. The cause is the obligation to retire polluting units at the Dhekelia and Vasilikos power stations at the end of 2029.
The figures. According to AKEL secretary general Stefanos Stefanou, the EU requires units of about 720 MW to be retired from 1 January 2030, almost half of conventional generation. Philenews notes that the old boilers at Dhekelia alone account for 360 MW, and if units 1, 2 and 3 at Vasilikos are also retired, the loss will reach or exceed 700 MW out of the roughly 1,400 MW that EAC can theoretically generate from oil today.
What was said. House President Annita Demetriou (DISY) asked “what will we tell people” if in 2030 the country can produce only half of the electricity it needs. DIKO MP Chrysis Pantelides called supply adequacy “a national issue” and urged the President of the Republic to cooperate with the parties. Stefanou said the government activated the capacity mechanism very late and cited estimates that the cost per kilowatt-hour could exceed 40 cents, from just over 30 cents today.
Context. The chairman of the energy committee, Nikos Georgiou (DISY), called for back-up capacity to be found urgently and cited Ireland, which paid almost €1.5 billion through a capacity mechanism. According to Philenews, almost all speakers said that storage, due to be installed within one to two years, cannot on its own cover the loss of generation.
The GSI cable. Stefanou also criticised the cost of the Great Sea Interconnector with Greece, now estimated at €1.9 billion against €1.2 billion initially, and called for an independent assessment, according to Politis and Cyprus Mail. Annita Demetriou said that for DISY the project is a matter of energy security and national strategy.