Grid5 Nov 2026

Brno prepares heat pipeline from Dukovany: CZK 17.8 billion, nuclear heat from 2032

Teplárny Brno has spun off heat distribution into a new company, TB Distribuce, which will build and operate the roughly 42-kilometre hot-water pipeline from the Dukovany nuclear power plant. According to managing director Martin Šroubek, the heat is due to reach Brno from 2032, and the share of gas in heat production should fall from 62% to around 7%.

EuroEnergy Newsroom · Czechia · 1 min read

Clădirea administrativă și coșul de fum al centralei de termoficare Špitálka a companiei Teplárny Brno, în Brno
Foto: Bernhard Holub · CC BY-SA 4.0 · Wikimedia Commons

The city of Brno wants about half of its district heating to come from the Dukovany nuclear power plant from 2032. Progress on the hot-water pipeline, estimated at CZK 17.8 billion, was outlined on 4 November in Ekonomický deník by Martin Šroubek, managing director of Teplárny Brno Distribuce, a newly created subsidiary of the heating company Teplárny Brno.

What has changed. TB Distribuce took over the primary network and the heat exchanger stations on 1 October, together with about 50 employees. Separating distribution from generation and sales was a condition for the subsidy. Nothing changes for customers: contracts remain valid.

The figures. The State Environmental Fund granted a subsidy of CZK 10.6 billion from emission allowance auction revenues, with TB Distribuce as the recipient. ČEZ is investing about CZK 3 billion in extracting heat from the plant. The route outside the city is about 42 kilometres long, from Dukovany to Bosonohy, and is being designed by AFRY CZ; around 53 kilometres are to be added within the city, according to oEnergetice.cz. According to e15, the project is to supply up to 2 million gigajoules a year to more than 100,000 households.

Context. According to Šroubek, the share of natural gas in the company's heat production will fall from 62% today to about 7%. Teplárny Brno and ČEZ signed an agreement on future heat supplies and an implementation agreement in March 2024.

What comes next. The documentation for selecting the contractor for the main route should be ready around the turn of 2026 and 2027; in 2027 come the contractor selection and land-rights preparation, followed by construction, trial operation and final approval.

Real-time data for the country are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page