Almaty: first gas turbine started at CHP-2; the modernised plant will have 557 MW
Kazakhstan's Ministry of Energy said the first gas turbine of the new combined-cycle unit at Almaty CHP-2 was fired up on 25 November, with electricity deliveries to the grid scheduled for 30 November. After modernisation, the plant will have 557 MW of electrical and 957 Gcal/h of thermal capacity, and emissions are expected to fall by more than 90%.
EuroEnergy Newsroom · Kazakhstan · 1 min read
Kazakhstan's Ministry of Energy announced on 26 November that the first turbine of the new combined-cycle (steam-gas) unit has been put into operation at Almaty CHP-2. The gas turbine, made by Siemens Energy, was fired up on 25 November, and electricity deliveries to the grid are scheduled for 30 November, according to the ministry statement carried by Kazinform and Sputnik Kazakhstan.
What comes next. Two more gas turbines are expected to be connected in December 2026. According to the publication Kursiv, the new unit will comprise three gas turbines and one steam turbine in total. Heat from the new hot-water boiler plant at CHP-2 has been supplied since 31 October.
The figures. After modernisation, the plant will be able to deliver 557 MW of electrical capacity and 957 Gcal/h of heat to the grid. The ministry estimates that once the plant has fully switched from coal to gas, pollutant emissions will fall by more than 90%, from 37,100 to 2,700 tonnes a year. “Sulphur dioxide and coal ash emissions will be almost completely eliminated,” the ministry said.
The technology. In a combined-cycle unit, the hot exhaust gases from the gas turbines are used to raise steam, which drives the steam turbine. At CHP-2, the three gas turbines will thus feed a single steam turbine, in addition to the heat supplied to the city.
Context. The ministry describes the project as particularly important for air quality in Almaty. Kursiv reported earlier that some of CHP-2's coal-fired boilers and turbines will remain in operation during the 2027–2029 transition period, and that the project documentation also provides for their use in the 2030s as a backup in case of disruptions to gas supplies.