Infrastructure

Installed capacity — Luxembourg

What Luxembourg could produce with everything running at once: installed capacity by source, as reported for 2026, next to how much has actually run.

Installed capacity
2,453MW
reported for 2026
Renewables
94.2%
2,312 of 2,453 MW
Largest source
Solar
1,575 MW · 64.2% of total
Against 2025
+1,488MW
154.2% against the previous year

The generation fleet, 2026

Installed capacity by source, as the operator reports it.

Installed capacity 2,453MW reported for 2026 Cleaner energy for tomorrow
Renewables 94.2% 2,312 MW
Largest source Solar 64.2%
Against 2025 +1,488 MW
Source Capacity (MW) Of total
Solar37,227 installations 1,575+1,031 64.2%
Onshore wind53 installations 479+268 19.5%
Biomass35 installations 191+106 7.8%
Natural gas 59−9 2.4%
Other sources88 installations 58+58 2.4%
Run-of-river hydro34 installations 57+35 2.3%
Waste 24 1.0%
Hydro reservoir 11 0.4%
Hard coal 0 0.0%
Geothermal 0 0.0%
Pumped-storage hydro 0 0.0%
Lignite 0 0.0%
Nuclear 0 0.0%
Oil 0 0.0%
Offshore wind 0 0.0%

How much ran at once

The highest output delivered at a single moment over the past twelve months, by source group, next to the installed capacity.

Of 2,453 MW installed, the most that ever ran at one moment was 501 MW — 20% of the fleet, on 06/07/2026, 14:45:00.

The peak is read from our own generation archive, not estimated: it is a lower bound on what the fleet can do. A small ratio means the group's sources never all ran together — reservoir hydro starts at peak demand, thermal plants sit idle when they are not called. A ratio above one hundred means the declared capacity has fallen behind: the figure is declared at the start of the year while new units come online during it. Groups are compared here rather than individual source types: the same source can report capacity under lignite and generation under coal, and at group level the two meet.

How it changed, year by year

Total installed capacity, from 2025 to 2026.

  1. 2026 2,453MW +1,488
  2. 2025 965MW

Luxembourg hosts the Vianden pumped-storage plant — 1,294 MW of turbine capacity, more than the rest of the Luxembourg fleet put together. It does not appear in the figures above, and not because they are missing it: the Luxembourg operator does not count it. Its output is fed into the German grid, and the plant is accounted for there. It stands physically in Luxembourg, but electrically it belongs to another system.

The figures come from the ENTSO-E Transparency Platform · Leneda — Creos Luxembourg: installed generation capacity by production type. The year is the one the operator reports for, not the year the figure was published.

Batteries are not here as a source of their own: they fall under “other”. The number of installations is, though — this country’s source counts them one by one, and the average per installation says on its own whether the fleet sits on roofs or in fields.